Necdet Bahadır Buluk argued that sustainability, structural safety and fire safety are one problem rather than three, using failed façades and tested curtain walls to show how detailing, validation and compartmentation set the length of a façade's working life.
Buluk's starting point is that façade engineering tends to treat sustainability, structural safety and fire safety as separate subjects, when in a real envelope they meet at the same joints and interfaces. In his framing, sustainability means reducing energy demand, environmental impact and the frequency of replacement. Structural safety means keeping reliable load paths and structural integrity. Fire safety means limiting ignition, hidden spread and the loss of compartmentation. He then traced sustainability across the whole life of a system: structural performance, corrosion and UV protection, thermal bridges and condensation at design stage; durability, embodied carbon and responsible sourcing in material choice; buildability, tolerances and quality assurance in delivery; cleaning, inspection and repair in operation; and disassembly, reuse and recycling at the end. Thinking beyond carbon, he said, the biggest lever is the service life a design actually achieves.
Service life lost in the detail
The evidence came from his firm's inspection work. On a government building in Ankara, the primary seals of a silicone-jointed curtain wall had deteriorated after 22 years under intense UV radiation. Buluk suggested a thin aluminium plate shielding the seal, or a ceramic coating on the outer surface, and estimated that such a slim stripe could have added another 10 to 15 years to the units. A very small detail, in other words, carries a large sustainability consequence.
Other cases followed the same pattern. An aluminium cladding substructure showed, after 25 years, not just surface corrosion but progressive section loss, and needed full replacement. On a commercial building the entire system had deformed after only 14 years: the cladding was just 3 mm thick for its panel size, and partial bonding to the substructure had removed the movement tolerances. On a second government building in Ankara, natural stone cladding had broken around its restraint points after 20 years, with half the façade affected. Stone is durable, Buluk stressed, but only if the whole system creates a correct load path.
Failure can also be immediate. A new overhead glazing system suffered severe condensation within a year because of a wrong glass specification and missing coatings on the proper surface, and the units had to be replaced. His closing point on sustainability concerned end of life: components do not share a service life, cladding ages faster than the substructure behind it, so removal of the cladding should be designed from the outset in order to keep the substructure.
Verify before procuring
Buluk divides structural safety into four stages: design basis, calculation, validation before procurement and site control. At Azure Tower in Batumi, his team designed a customised unitised curtain wall around a disassembly and glass replacement strategy, using a single pressure plate fixed every 25 cm with structural screws and protected by an inserted cover cap. Calculations covered not only frames and glass but anchor plates, anchor bolts and T-bolts, against a design wind load of 5,000 Pa, or 500 kg per square metre, and were then validated in an independent test centre under design, safety and repetitive ageing loads.
Testing earns its cost at ST Tower in Gzira, Malta, where large sliding doors sat within a stick system. In the first test a door accessory failed and the sash came off at around 2,200 Pa, against a 4,000 Pa design load. Replacing the deformed profile with a 3 mm stainless steel angle brought the retest to 6,590 Pa, which Buluk put at more than three times the failure load. A ventilation vent was reduced in size with the client and reached 5,250 Pa. On site, torque values, anchor pull-out resistance and material thickness are all checked.
Skipping validation has consequences he illustrated with panels and vents torn off an Istanbul building in a 2017 storm, likely annealed rather than safety glass in Hong Kong in 2018, and a glass plate falling from a tower, a failure that can kill people.
Fire as a design decision
Fire risk is managed in four stages: ignition, reaction, spread and containment. In a fire test on one of his UK projects, a brick slip cladding on an aluminium substructure was non-combustible throughout, yet it was the vertical and horizontal cavity barriers that stopped spread behind the cladding. On another high-rise, a sandwich of galvanised steel, rock wool and fire-resistant boards fixed to the slab is designed to hold for two hours even if frames and glass fail.
Combustibility class comes first, and Buluk's firm mostly specifies non-combustible or limited combustibility materials. Where combustible material is used, robust compartmentation is mandatory. In an Izmir residential building with natural wood ceilings and no compartmentation, fire spread across the whole building in minutes; he would have sealed each balcony vertically. His conclusion ties the three subjects together: measurable requirements in the brief, coordinated design, protected tested configurations in procurement, mock-ups in delivery and planned inspection through operation.